VCE-Braindumps understands the importance of all key topics of SAP Production Planning & Manufacturing with SAP ERP 6.0 EHP7 C_TSCM42_67 exam so that we prepare C_TSCM42_67 exam dumps material is prepared according to the C_TSCM42_67 exam pattern. You feel in the actual SAP C_TSCM42_67 exam confident enough to attempt each C_TSCM42_67 exam question perfectly. Just check the C_TSCM42_67 exam free demo first to have an idea what exactly VCE-Braindumps has prepared for you and offering with Money Back Guarantee!

♥ VALID C_TSCM42_67 Exam Questions 2018 ♥

C_TSCM42_67 exam questions, C_TSCM42_67 PDF dumps; C_TSCM42_67 exam dumps:: https://www.dumpsschool.com/C_TSCM42_67-exam-dumps.html (160 Q&A) (New Questions Are 100% Available! Also Free Practice Test Software!)

Latest SAP C_TSCM42_67 Dumps Exam Questions and Answers:

Version: 5.0
Question: 1

You want to use the different options for planning in SAP ECC. What is the correct sequence of the
planning procedures?
Please choose the correct answer.
Response:

A. Sales and operations planning -> Demand management -> Long-term planning -> Material
requirements planning -> Capacity planning
B. Demand management -> Sales and operations planning -> Capacity planning -> Long-term
planning -> Material requirements planning
C. Material requirements planning -> Demand management -> Sales and operations planning ->
Long-term planning -> Capacity planning
D. Long-term planning -> Sales and operations planning -> Demand management -> Material
requirements planning -> Capacity planning

Answer: A

Question: 2

You want to use production/resource tools in your manufacturing process. Which production type do
you use?
Please choose the correct answer.
Response:

A. Repetitive manufacturing
B. Production order
C. Process order
D. KANBAN

Answer: B

Question: 3

For which of the following objects can you enter a confirmation?
There are 2 correct answers to this question.
Response:

A. Production order
B. Production order operation
C. Trigger Point
D. Work Center

Answer: AB

Question: 4

Which of the following master data can be used with process orders?
There are 3 correct answers to this question.
Response:

A. Serial numbers
B. Master recipes
C. Resources
D. Production/resource tools
E. Production versions

Answer: BCE

Question: 5

You want to use the function “Read PP master data” in the production order. However, while calling
the function you receive an error message. What could be the reason?
Please choose the correct answer.
Response:

A. The material availability check has been performed.
B. Goods movements have been posted.
C. The production order has been released.
D. Order papers have been printed.

Answer: B

Question: 6

How can you convert planned orders into production orders in an SAP ECC system?
There are 3 correct answers to this question.
Response:

A. Automatically, in the planning run (MRP)
B. Set the conversion indicator in Customizing for the planned order.
C. Use mass processing.
D. Use the order progress report.
E. Use background processing.

Answer: CDE